Birds of Prey Aviary Project

Watch Our Progress!

Photo credits: Adam Lewis, Callie Bowdish, John O'Brien, Darlene Chirman

SBAS Birds Of Prey Campaign Kick-off Event at the Santa Barbara Museum of Natural History

July 11, 2009

plans plans
Building Plans Artist's Drawing of Project
old garage Max and Gabriele
Symbolic destruction of old garage Gabriele with Max, future resident of the Aviary

SBAS Aviary Groundbreaking at the Santa Barbara Museum of Natural History

May 22, 2010

attendees breaking ground
Donors, Friends and other Attendees Finally, the moment we have been waiting for: BREAKING the GROUND!
old garage breaking ground
DOWN with the old garage; Make room for the new AVIARY!

SBAS Annual Member Picnic and Walk to the Aviary Site

July 17, 2010

John & Darlene John & Darlene
Initial grading uncovered an old well (under the boards) John O'Brien provides project oversight for Audubon, standing with Board President Darlene Chirman

Grading the Site

August 2010

gravel
Investigation of well and additional permitting delays project Filling surprise well with gravel
breaking ground filled site
Dave with rock selected for donor plaque Grading completed, after 2-month delay - August 29

Finally, It's Taking Shape!!!

September 2010

John & Darlene framing
Marking the footing layout Framing the footings
cementing marking floor
Cementing the floor and footings; Best Bid: Donn Roberts Construction Our signature and date
framing framing
West wall framing goes up - September 21 Early steel framing
framing framing
Steel roof beams in place - September 29 Boulder incorporated as perch in peregrine enclosure

Moving Right Along. . .

October 2010

plywood exterior siding
Plywood siding started - October 7 Exterior siding goes on West side
covering hip roof rain
Hip roof gets covered Construction in the rain; North side has two bird windows, South side has just one.
east side rain
East side from visitor angle Birds' view looking to the East

One Month From Completion (YES!)

November 2010
So Much Happening - Almost Done!

exterior front windows
Exterior prior to final siding Birds' window openings will be screened
donor plaque boulder peregrine boulder perch
Donor plaque boulder Peregrine enclosure with boulder perch
tar paper peregrine boulder perch
Hardi panel exterior siding should be complete by Tuesday, November 23. Skylights are in, all the doors are in, hardware will be put on doors next week. Electrical and plumbing are done. Sink has been ordered. Roof/ceiling insulation is installed. Plaque boulder moved into place. WE CAN'T WAIT AND NEITHER CAN THE BIRDS! (Note the beautiful persimmon tree full of fruit on the birds' view side of the building!)
front stoop concrete pad
Front stoop goes in Concrete pad being poured
more siding window sills
Final siding Window sills get ready for netting

SO CLOSE!

December 2010
It's Been a L O N G   T I M E   C O M I N G !

ADA parking windows
ADA parking space and front stoop are in Outside wall final prepped and painted to match small cottage.
final painting look into enclosures
Final painting touches on the birds' side of the building Closer look into the enclosure walls

Website information contacts:
Chapter office address:
5679 Hollister Ave., Suite 5b
Goleta, CA 93117
805-964-1468

Chapter email
Website by:
Technical Specialties
©Copyright 2010, Technical Specialties

Updated: November 26, 2010